Understand · ERP, simply explained

What is an ERP?

This page sells nothing. It explains what an ERP is, how a project unfolds and the words you’ll hear.

ERP stands for Enterprise Resource Planning: a single piece of software that brings together the management of the whole company.

Read this before you sign anything.

1 · The patchwork

Before the ERP: the patchwork

In many companies, each department has its own tool: quotes in a spreadsheet, stock updated when someone remembers, invoices keyed in twice. One by one, they work; together, they don’t talk.

A customer asks where their order is: answering takes three files and a call to accounting. Three tools, three versions of the truth.

2 · One single system

What “one single system” really means

With an ERP, reference CDE-0042 is entered once, on the quote; each following document is generated from the previous one. Whoever picks up sees everything in one place.

Illustration 1 · One reference, five documents
N°DocumentReferenceWhat happens
01QuoteCDE-0042Entered once.
02OrderCDE-0042Confirmed in one click.
03DeliveryCDE-0042Stock is updated on its own.
04InvoiceCDE-0042Generated from the delivery.
05Journal entryCDE-0042Posted automatically.

Illustrative example: the same number runs through all five documents.

Nobody re-typed anything.

3 · The scope

What an ERP covers

One module per major area; you switch on the ones you need. They all share the same database.

  • Sales

    Quotes, orders, price lists.

  • Purchasing

    Requests for quotation, supplier orders, receipts.

  • Inventory

    Receipts, deliveries, locations, stock counts.

  • CRM

    Customer relationships: contacts, leads, opportunities.

  • Manufacturing

    Bills of materials, manufacturing orders.

  • Accounting and finance

    Invoices, payments, journal entries, cash.

  • Human resources

    Employees, time off, expenses.

  • And more…

    Projects, website, customer service: the list depends on the software you choose.

4 · The signs

Signs it’s time to think about it

No magic threshold: situations that keep coming back, telling you your tools can’t keep up.

  • The same information is entered several times

    On the quote, then on the invoice, then in accounting.

  • Two files, two figures

    And nobody really knows which one is right.

  • To know real stock, you have to go and count it

    Before promising a date, someone checks by hand.

  • Month-end starts with a collection run

    Gathering everyone’s files before you can close the books.

  • Only one person knows “the” file

    When they are away, part of the business has to wait.

  • The company is changing scale

    A new site, a new activity, a new obligation, such as the French e-invoicing reform, under which every company in France has had to be able to receive e-invoices since 1 September 2026.

5 · How it unfolds

How an ERP project unfolds

The names change from one integrator to another; the steps stay the same.

  1. 01
    Scoping

    Describe how you work today (AS IS) and tomorrow (TO BE). The gap is the work to do.

  2. 02
    Configuration

    Set up what the software already does; write code only when the need isn’t covered.

  3. 03
    Data migration

    Decide what moves into the new system, clean it, import it.

  4. 04
    Acceptance testing

    Your teams test on real cases; fixes come before go-live.

  5. 05
    Training

    Everyone learns their own tasks, on your data.

  6. 06
    Go-live

    The new system becomes the reference; the old one stops.

  7. 07
    Follow-up

    Adjustments, questions, enhancements, new versions: an ERP lives with the business.

6 · The choices

The choices to make

Four questions before comparing software, none with a universal answer.

Illustration 2 · Four questions before comparing
N°QuestionOn one sideOn the otherTo check
01Vendor and integratorThe vendor designs the software, keeps it evolving and sells the right to use it: the licence.The integrator sets it up for you: scoping, configuration, data migration, training.They may be two companies, with two contracts and two invoices. Ask who does what, and who bills you for what.
02Cloud or serverCloud (SaaS): the vendor hosts the software, updates it and backs it up. You use it from a browser, on a subscription.Server: on your premises or at your hosting provider. You keep control of the infrastructure, and you take on its security, backups and updates.Who handles backups and updates, and what the contract says.
03Standard or customStandard: you set up what the software can already do. The vendor’s updates follow the same path.Custom: code is written for a need the standard doesn’t cover. That code then has to be maintained, and adapted to each new version.For each proposed development, what it costs to write, then to maintain.
04Fixed price or day rateFixed price: the price is set in advance, for a written scope. Anything outside it goes through an amendment.Day rate: you pay for the time actually spent. It is flexible, and the final budget follows that time.Which document the price rests on, and how a change in scope is handled.

Source: common practice on ERP projects, across all vendors.

7 · The glossary

The glossary, without jargon

The words of any ERP project, without jargon.

Illustration 3 · Glossary
WordWhat it means
ERPOne single piece of software where your sales, purchasing, inventory and accounting live, instead of separate tools you have to reconcile by hand.
DatabaseWhere the software stores its information. A single database: each customer, product or invoice exists in it only once.
ModuleA block of the ERP dedicated to one area: sales, purchasing, inventory… You switch on the ones you need; they share the same database.
VendorThe company that designs the software, keeps it evolving and sells its licences.
IntegratorThe company that sets the software up for you: scoping, configuration, data migration, training, follow-up.
LicenceThe right to use the software, paid to the vendor, often as a subscription, for example per user per month. It is separate from the integrator’s fees.
SaaSSoftware as a Service: the software is hosted by its vendor and used from a browser, on a subscription. Hosting, updates and backups are the vendor’s job.
AS IS / TO BEHow you work today / how you will work. Scoping measures the gap between the two.
ConfigurationSetting up what the software can already do (taxes, approval flows, catalogues) without writing code.
Custom developmentBespoke code written for a need the standard doesn’t cover. It has to be maintained, and adapted to each new version.
Data migrationMoving your customers, products and history into the new system. Its scope is decided in writing, before you start.
Acceptance testingTests run by your own teams, on real cases, to check the system does what was planned.
Go-liveThe day your teams work in the new system, no longer in the old tool. It has to be prepared, training included.
Fixed price or day rateA fixed price sets the cost up front, for a written scope. A day rate bills for time spent: the final budget follows that time.

Source: common ERP project vocabulary.

8 · And Odoo?

And where does Odoo fit?

All of the above applies to any ERP. The one we implement is Odoo, published by Odoo SA: its page explains the editions, hosting and pricing.

Got the idea?